PHASE -1A

INSTALLMENT PAYMENT SCHEDULE
On Application Rs. 50,000/-
Within 30 days of Application 20% of the Flat Cost+ Legal fees, less application amount
On Commencement of Foundation 10% of the Flat Cost
On Commencement of Basement/Podium 10% of the Flat Cost
On Commencement of Ground Floor Roof Casting 10% of the Flat Cost
On commencement of 2nd Floor Roof casting 10% of the Flat Cost
On commencement of 4th Floor Roof casting 10% of the Flat Cost
Within 30 days of 4th Floor Roof casting 50% of Club Membership + 50% of Car Parking
On commencement of 7th Floor Roof casting 10% of the Flat Cost
On commencement of 9th Floor Slab 10% of the Flat Cost
On commencement of flooring 5% of the Flat Cost + 50% of Club Membership + 50% of Car Parking
Before Possession as & when demanded Additional Charges as mentioned above
On Possession 5% of the Flat Cost

Note: We will demand transformer charge as and when required
Service Tax as applicable & subject to change with the changed notification by the statutory body.
All Payments to be made in the name of "SOUMITA CONSTRUCTION PVT. LTD.
Account Name: Soumita Construction Pvt. Ltd.
Payment received in cheque is subject to realisation of the cheque.

PHASE -1A

DOWN PAYMENT SCHEDULE - 8% DISCOUNT ON BSP
On Application Rs. 50,000/-
Within 15 days of Application 10% of the Flat Cost+ Car Parking + Legal fees, less application amount
Within 15 days of Agreement 80% of the Flat Cost & Car Parking + 50% Car Parking
Before Possession as & when demanded 50% of the Cub Membership + Additional Charges as mentioned above
On Possession 10% of the Flat Cost

Note: We will demand additional charge as and when required.
No discount is applicable on CP, PLC or Floor Rise charge.
Service Tax as applicable & subject to change with the changed notification by the statutory body.
All Payments to be made in the name of "SOUMITA CONSTRUCTION PVT. LTD.
Payment received in cheque is subject to realisation of the cheque.